Basement finishing in Minneapolis–St. Paul
Twin Cities basements are old: the median home in Minneapolis was built in 1951 and in St. Paul in 1952.1 Minneapolis's basement finish guide is written for exactly those houses, with rules for low ceilings and old stairs that decide whether a room can legally be a bedroom.2
Ceiling rule
Habitable basement space needs 6'4" from floor to the lowest beam or duct; below that it's non-habitable.2
Old housing
72% of Minneapolis homes and 78% of St. Paul homes were built before 1980.1
Permit
Minneapolis requires a building permit and plan review for a basement finish.3
Basement finishing cost
What does basement finishing cost in Minneapolis–St. Paul?
What it costs to finish a basement in the Twin Cities: national per-foot ranges, how Minneapolis permit fees are figured, and the code items that add cost.
Read the guide →Egress windows
Egress windows in Minneapolis–St. Paul
Basement egress windows in the Twin Cities: size rules, window wells, the 2-foot zoning setback, the sprinkler exception and national installed costs.
Read the guide →Habitable or not: the 6'4" rule
Minneapolis says bedrooms, other habitable rooms and the exit path to the stairs or outside door need a ceiling height of at least 6 feet 4 inches, measured to the lowest projection, including beams, girders and ducts. In an existing basement where 6'4" can't be reached, the space is considered non-habitable. It can still be finished, just not as a bedroom or living space.2
Habitable rooms must be at least 70 square feet and at least 7 feet in every horizontal direction.2 Watch the soffits. Floor under a furred-down ceiling lower than 7 feet, or a sloped ceiling under 5 feet, does not count toward that 70 square feet.2 Big duct boxes can shrink a planned bedroom below the minimum.
Adding a bedroom
- Egress: an exterior door or an egress window with at least 5.7 sq ft of opening, 20" wide, 24" high, and a sill no more than 44" above the floor. See Twin Cities egress windows.2
- Light and air: window glass equal to 8% of the floor area and openable area of 4%, or mechanical ventilation and artificial light as alternatives.2
- Heat: able to hold 68°F in every habitable room.2
- No fuel-fired appliances in, or drawing combustion air from, bedrooms, bathrooms or closets.2
Window wells and the 2-foot rule
A below-grade egress window needs a window well. The Minneapolis guide lists these rules:2
- At least 9 square feet of floor area, and at least 36 inches each way, so the window opens fully.
- A fixed ladder or steps if the well is more than 44 inches deep.
- Drainage to the foundation drain system or another approved method.
- At least 2 feet from any side or rear property line. This is a zoning rule, so narrow city lots can limit where a well goes.
- Under a deck or porch, a clear path at least 36 inches high to the yard.
Adding a basement bathroom
Bathrooms aren't habitable rooms, but they have their own height rules in existing basements:2
- 6 feet 4 inches of ceiling height at the center of the clear area in front of the toilet and sink.
- 6 feet 4 inches above a 30-by-30-inch area at the wall where a showerhead is mounted.
- Sloped ceilings and soffits are fine elsewhere, as long as they stay out of those spaces.
Also plan for enclosed storage under the stairs. If it has a door or access panel, the walls, underside of the stairs and soffits inside it need 1/2-inch drywall.2
Smoke and CO alarms
When permitted work removes wall or ceiling finishes, or a bedroom is added, the home needs smoke alarms placed as for new construction, interconnected and hardwired. Carbon monoxide alarms go outside and within 10 feet of each sleeping area, on every level with bedrooms, under Minnesota Statutes 299F.50.2
Ready to price your Twin Cities basement?
One short form connects you with one independent local basement finishing contractor who serves your area. Free for homeowners, no obligation.
Get my free quoteTakes under a minuteOld basement stairs
Existing stairs serving a finished habitable basement must meet minimums including 30" width, 6'4" headroom, an 8" maximum rise, a 9" minimum run, and a handrail 30" to 38" high.2 Steep original stairs are common in older Twin Cities homes, so have a contractor measure them before you price the project.
Test for radon before and after you finish
A finished basement is where radon matters most, because it's the level closest to the soil and you'll now spend time there. The Minnesota Department of Health (MDH) says more than 2 in 5 Minnesota homes have radon levels that pose a significant health risk, and the state's average level is more than three times the U.S. average. MDH recommends testing every Minnesota home.7
- Test before and after. MDH says to test before and after you make changes to the home, and names finishing a basement first in its list. Other examples include adding insulation, replacing windows and changing the heating or air conditioning.8
- Test the right spot. MDH says to test the lowest level you use regularly. If you'll spend more than 10 hours a week in the new basement, test there. Place the kit at least 20 inches above the floor, away from drafts, kitchens, bathrooms, laundry rooms, fireplaces and furnaces.8
- What the numbers mean. Start with a short-term test (2 to 7 days). From 2 to 7.9 pCi/L, MDH says to follow up with a long-term test; at 8 pCi/L or higher, a second short-term test. After the follow-up, MDH recommends mitigating at 4 pCi/L or more and says to consider it from 2 to 3.9.8
- Hire a licensed mitigator. Anyone doing radon mitigation in Minnesota must be licensed by MDH. MDH warns against unlicensed installers and quotes under $1,000, and says to hold final payment until a test shows lower levels.9
If a mitigation system may be needed, it's easier to plan the pipe route before the walls and ceiling go up. Our sister site has more on radon testing in Minneapolis.
Inspection details people miss
These come from the same Minneapolis basement finish guide, and they are easy to miss on a plan:2
- The window well must extend 8 inches past each side of the window, to keep wood away from soil and prevent rot. A ladder or steps in a deep well can't stick more than 6 inches into the required well space.
- Bars, grilles or well covers over an egress window must release from the inside without a key, tool or special knowledge. Specific security grille systems need the city's approval before they go in.
- No openable window? There are alternatives. A bedroom without natural ventilation can use a mechanical system that provides 0.35 air changes per hour in the room. A whole-house system can supply 15 cubic feet per minute of outdoor air per occupant, counting two for the first bedroom and one for each additional bedroom. Artificial light must average 6 foot-candles at 30 inches above the floor if window glass falls short.
- Stairs need a light and a guard. Interior stairs need artificial lighting over the landings and treads. Where a guardrail is new or required, it must be at least 36 inches high, with openings under 4 inches.
- Each bedroom needs its own egress. When a basement has bedrooms, each bedroom needs its own egress window or door; the adjoining areas of the basement don't need a separate one. A full sprinkler system that meets the code can take the place of egress for new basement bedrooms.
St. Paul and the suburbs
The rules above come from the City of Minneapolis guide, which is based on the 2020 Minnesota Residential Code.2 Because that code is statewide, St. Paul and suburban building departments enforce the same core rules, but each city runs its own permits and fees; check with the city where the house is.
Check the contractor's Minnesota license
Minnesota requires a residential building contractor or residential remodeler license for anyone who contracts directly with a homeowner (1 to 4 units) for work in more than one skill area.5 A basement finish usually mixes framing, drywall, insulation and flooring, so the company you hire directly should be licensed. A remodeler license covers existing homes, which includes basements.5 Homeowners working on their own house don't need a license.5
Look the company up on the Minnesota Department of Labor and Industry's license lookup before you sign.6
Choosing a basement contractor in the Twin Cities
Ask the contractor to confirm ceiling heights under the ducts and beams before promising a bedroom, and to show how they'll handle egress, stairs and alarms. Then compare bids using the Twin Cities cost guide.
Areas we serve
We match homeowners across the Twin Cities area, including these communities and ZIP codes:
- Minneapolis55401 · 55402 · 55403 · 55404 · 55405 · 55406 · 55407 · 55408 · 55409 · 55410 · 55411 · 55412 · 55413 · 55414 · 55415 · 55417 · 55418 · 55419 · 55454 · 55455
- St. Paul55101 · 55102 · 55103 · 55104 · 55105 · 55106 · 55107 · 55108 · 55114 · 55116 · 55117 · 55119 · 55130 · 55155
- Bloomington55420 · 55425 · 55431 · 55437 · 55438
- Edina55424 · 55435 · 55436 · 55439
- Eden Prairie55344 · 55346 · 55347
- Minnetonka55305 · 55343 · 55345
- Plymouth55441 · 55442 · 55446 · 55447
- Maple Grove55311 · 55369
- Brooklyn Park55428 · 55443 · 55444 · 55445
- Coon Rapids55433 · 55448
- Blaine55434 · 55449
- Roseville55113
- Woodbury55125 · 55129
- Eagan55121 · 55122 · 55123
- Burnsville55306 · 55337
- Lakeville55044
ZIP codes are 2020 Census ZIP Code Tabulation Areas, which closely approximate USPS ZIP codes. We list ZIPs that make up a substantial share of each community, so edge ZIPs that barely touch a town are left out, and some ZIPs span two towns.4 Not on the list? Send the form anyway, and we'll tell you if we can help.
Common questions
What ceiling height does a finished basement need in Minneapolis?
6 feet 4 inches from the finished floor to the lowest beam, duct or other projection for habitable space. If an existing basement can't reach that, it can only be finished as non-habitable space.
Can I add a basement bedroom in Minneapolis?
Yes, if it meets the ceiling height, is at least 70 square feet and 7 feet in each direction, and has an egress window or exterior door, plus light, ventilation, heat and alarms.
Do I need a permit to finish a basement in Minneapolis?
Yes. Minneapolis requires a building permit and plan review for basement finishes.
Are St. Paul's rules the same?
The Minnesota Residential Code applies statewide, so the core rules match, but St. Paul runs its own permit process and fees.
How deep can a basement window well be without a ladder?
In Minneapolis, a window well deeper than 44 inches needs a permanently attached ladder or steps that work with the window fully open. The well must also be at least 9 square feet and 36 inches each way.
Does my basement contractor need a Minnesota license?
Yes, if they contract with you directly for work in more than one skill area, such as framing plus drywall and flooring. They need a Minnesota residential building contractor or remodeler license. You can check it on the Department of Labor and Industry's license lookup.
Should I test for radon before finishing my basement in Minnesota?
Yes. The Minnesota Department of Health says to test before and after changes to the home, including finishing a basement, and to test the lowest level you use regularly. MDH recommends mitigating at 4 pCi/L or higher.
Does every room in a finished basement need an egress window?
No. Minneapolis's guide says each basement bedroom needs its own egress window or exterior door, but adjoining areas of the basement don't need a separate one. A code-compliant sprinkler system can replace egress for new basement bedrooms.
Can a basement bedroom pass without an openable window?
Ventilation can be mechanical instead: 0.35 air changes per hour in the room, or a whole-house system with 15 cubic feet per minute per occupant. The bedroom still needs an egress window or exterior door, and artificial light can replace missing window glass.
General information summarized from the public sources listed below. It isn't professional, engineering or legal advice. Codes and programs change; confirm current requirements with your local building department or utility before you start.
Sources
- U.S. Census Bureau, American Community Survey 2020–2024 5-year estimates, tables B25035 (median year built), B25034 (year built), B25003 (tenure), B25077 (median value)
- City of Minneapolis, "Basement finish or remodel in one and two-family dwellings" (PDF)
- City of Minneapolis, "Basement Finish" building requirements
- U.S. Census Bureau, 2020 ZCTA-to-place relationship files
- Minnesota Department of Labor and Industry, "Residential contractor licensing"
- Minnesota Department of Labor and Industry, "License and registration lookup"
- Minnesota Department of Health, "Radon in Homes"
- Minnesota Department of Health, "Radon Testing"
- Minnesota Department of Health, "Find a Radon Mitigation Professional"